Turbines and engines

  1. Behind the meter Turbines and engines

    Wärtsilä Says Lead Times for Its Engines Continue to Increase, Given Strong Energy Order Intake

    In its interim report release of October 27, 2026, Wärtsilä says that lead times for its engines continue to increase, given strong Energy order intake, and reports an order to supply an onsite power solution for a data center project in the United States.

  2. Behind the meter Turbines and engines

    An Award to Make Gas-Fired Power Units for a Data Center: Enerflex's Material Change Report of October 13, 2026

    Enerflex Ltd. reported on October 13, 2026 that it has been contracted to design, engineer, fabricate and assemble "over one gigawatt" of natural gas-fired power generation units for a large data center development in North America. The report also says what its backlog offers beyond the initial equipment scope.

  3. Behind the meter Turbines and engines

    Booked, Shipped and Reserved: Gas Services in Siemens Energy's Analyst Presentation for Q3 FY26

    Siemens Energy's analyst presentation of August 5, 2026 lists, under "Gas Services," gigawatts booked and shipped and a backlog of firm customer commitments beside slot reservations, and it shows announced capacity expansions for two size classes of gas turbine.

  4. Behind the meter Turbines and engines

    Gas Turbines Among the Awards: Baker Hughes' Results for the Second Quarter of 2026

    Among the awards in Baker Hughes' results release of July 26, 2026 are gas turbines for power in North America, with data centers named among the uses. The release also gives the orders and the Remaining Performance Obligations of the segment that won them.

  5. Behind the meter Turbines and engines

    Slots, Orders and a Plan for Output: GE Vernova's Gas Turbine Numbers for the Second Quarter of 2026

    GE Vernova's results release of July 22, 2026 says its gas power equipment backlog and slot reservation agreements grew within the quarter, and that it anticipates more by year-end. It also gives figures for annual gas turbine output in the third quarter of 2026, in 2028 and in 2030.

  6. Behind the meter Turbines and engines

    Record Orders and Longer Equipment Delivery Times: Wärtsilä's Half-Year Report for January to June 2026

    Wärtsilä's release of July 21, 2026 says Energy order intake passed its previous all-time high, largely as a result of firm data center-related orders across two projects and of balancing orders. Its chief executive also says equipment delivery times continued to increase.

  7. Behind the meter Turbines and engines

    Difficult to Answer With a Standard Lead Time: Mitsubishi Heavy Industries' Q&A Summary for Q1 FY2025 on Gas Turbines

    In its own summary of the questions and answers at its briefing of August 5, 2025, Mitsubishi Heavy Industries said lead time for large-frame gas turbines varies by project, and that many of the projects asked about will begin commercial operation between FY2028 and FY2030. It also gave its plan to increase production capacity.

  8. Behind the meter Turbines and engines

    Hardly Any New Gas Capacity in 2024, and a Plan for More: EIA on Combined-Cycle Plants Through 2028

    Hardly any new natural gas capacity came online in the United States in 2024, a June 2025 note from the U.S. Energy Information Administration says. Developers plan more combined-cycle capacity through 2028, and the note says how much of that plan is already under construction.