Tritax Big Box, which describes itself as "the largest listed investor in high-quality logistics warehouse assets," published its results for 2025 on February 27, 2026. Beside its warehouses, the results set out a data center strategy the company calls "power-first." Parts of the results follow, not the whole, and the company's own financial targets are not reported here.
Power Before Land
The company says it chose this approach "recognising the acute scarcity of deliverable grid connections." In key availability zones, it says, "the wait times for power connections are more than 10 years, which significantly restricts development of data centres in these locations."
Its model, as the results list it, draws on the company's understanding of the UK power network and its relationships with utility companies. It "identifies and secures existing grid connection agreements in key data centre locations," and it "identifies and secures appropriate sites." The company says this can make its developments "income producing up to a decade earlier than following the traditional real estate model of securing the land first."
In this model the grid connection agreement is the scarce asset, and the site is found to suit it.
Fitting Out, Operating and Maintaining
Typically, the results say, the company will "provide the client with a powered shell, in which the client is responsible for fitting out, operating and maintaining the data centre." Its first site is Manor Farm, at Heathrow, within the Slough Availability Zone, bought in January 2025. At the same time the company formed a 50:50 joint venture with a renewables company, "enabling accelerated power delivery to the site using existing grid connection agreements, with 107MW to be provided in H2 2027 and 40MW in 2029." That connection, the results add, is "supported by utility-scale battery storage."
The company says it is "in negotiations on a potential pre-let with an occupier following two rounds of competitive bidding." When the results were published, it was awaiting a planning decision from the Secretary of State, which the Planning Inspectorate had indicated would be made "on or before 17 March 2026."
For a client fitting out a powered shell here, the dates that matter are the ones for the power: the second half of 2027, and 2029.
A Second Site
The company's second site, secured in the first half of 2025 "in the broader London availability zone," has "an initial 125MW of power with the potential for future expansion." Its planning application went in "towards the end of 2025."
Among its priorities for 2026, the results list the aim to "achieve planning, a pre-let and commence construction of 107 MW data centre scheme at Manor Farm, Heathrow."
Will Manor Farm's power arrive on the dates the results give?
Sources
- Tritax Big Box REIT plc. Results for the year ended 31 December 2025. 27 February 2026. company filing