Texas Water Board Memo Recommends Denying a Petition on Data Center and Crypto-Mining Water

A memo for the Texas Water Development Board's meeting of July 23, 2026 recommends denying a petition for a dedicated industrial water-use category for data centers and crypto-mining. The agency, it says, is currently working on methods for a sub-category within manufacturing for large-load digital infrastructure, to be used for the next planning cycle.

In Texas, regional and state water planning is a five-year process, according to a memo of the Texas Water Development Board. Each planning cycle uses new projections of how much water will be needed.

In May 2026, a group of petitioners asked for a change. They wanted the agency to give data centers and crypto-mining an industrial water-use category of their own. The memo, written for the board's meeting of July 23, 2026, carries the recommendation of the agency's executive administrator. It is to deny the petition.

The memo is a recommendation to the board. It does not say what the board decided. Parts of it follow, not the whole.

Illustration

What the Petitioners Asked For

The petition was submitted on May 29, 2026, the memo says. It met all requirements of the state's Administrative Procedures Act and of the board's rule on such petitions. It asks the agency to adopt a rule to "establish a dedicated industrial water-use category for Data Centers and Crypto-Mining operations."

It also asks for standalone water demand projections for hyperscale data centers and crypto-mining facilities. And it asks that the most current peer-reviewed high-growth data be used to update the draft 2027 State Water Plan, among other documents. It gives the findings of a university white paper of May 2026 as an example of such data.

Why the Memo Recommends Denial

The executive administrator gives three reasons for denying it.

It is too late in the 2026 regional water planning process, the memo says, to update demand projections. It is also too late to complete a rulemaking that would affect the requested documents and the financial assistance framework.

The agency is also currently working, the memo says, on methods to include a sub-category within manufacturing for large-load digital infrastructure. That sub-category is to be used for the next planning cycle.

And the categories and methods for demand projections are not located in the agency's rules. So a rulemaking, the memo says, is not the appropriate way to meet this request.

On the timing, the memo says draft demand projections for the 2026 regional water plans were developed in the second half of 2021. The board adopted the final projections in November 2023. The regional planning groups adopted their plans by October 20, 2025. The board approved them on January 22, 2026.

There was limited data available on this category of water use, the memo says. That was so for the 2026 regional plans and for the 2027 State Water Plan.

Demand Projections, Now and in the Next Cycle

The agency is enhancing its data collection and analysis, the memo says. The aim is to improve its projections of the water demands of high-load digital infrastructure for future state water planning cycles. As the sector grows, it says, this water use category will report and fall more comprehensively within the agency's manufacturing water use projections. That is largely because of direct use reporting.

The agency plans to project a separate sub-category within manufacturing for large-load digital infrastructure. That process, the memo says, will be ready to use in the demand projections for the 2031 regional water plans. The agency anticipates releasing draft non-municipal projections to the planning groups in 2027.

The agency builds its draft demand projections, the memo says, from a broad set of data sources. These include self-reported water use data from industrial facilities, published peer-reviewed research on sector water use, and federally developed data sets. During a review period, planning groups provide locally available information. The memo gives examples. One is evidence of new or existing facilities not included in the agency's Water Use Survey. Others are plans for new construction or expansion of facilities, and evidence of errors in reported past water use.

The executive administrator recommends denying the petition. Even so, the memo says, the agency has already begun the actual work the petition requested.

The petition asked for the change in this cycle. The memo answers with the next one.

Sources

  1. Texas Water Development Board. Agenda Item Memo, Board Meeting of July 23, 2026: Petition for Rulemaking Related to Water Plan Demand Projections (with its attachment). 23 July 2026 (the memo prints 'BOARD MEETING DATE: July 23, 2026'). regulator