Nebius runs an AI cloud. Some of the capacity behind it sits in sites the company builds. Some sits in colocation sites.
Where it relies on third parties, its letter for the third quarter says, "there have been delays." The letter is dated November 12, 2026. Some third-party capacity it expected to come online this year is now scheduled for the first half of 2027. The contracts behind that capacity remain in place, it says.
For a site in New Jersey, the letter gives a reason. Parts of the letter follow, not the whole.
The Schedule in New Jersey
In New Jersey, Nebius has capacity contracted with a customer. It now expects to have delivered more than half of that capacity by the end of the year. The remaining tranches are now scheduled for the second quarter of 2027.
Late in the third quarter, the letter says, the third party there started to retire some of the site's temporary generation, ahead of the move to permanent power. "That decision reset the schedule for the remaining tranches." The customer, Nebius says, has been part of the planning process.
The letter says Nebius is deploying fuel cells as the main power source. That generation is already online, it says, and is being scaled up. Nebius expects to deliver additional capacity over the next few weeks.
A delivery date can move on a power decision made by someone else. Contracted capacity is not yet delivered capacity.
Shifts in Colocation Timelines
Delivery dates at "a number of colocation sites" shifted into the first half of 2027, the letter says, including the remaining New Jersey tranches.
A heading in the letter says these shifts "do not reflect structural change." Nebius says it is confident it can bring this capacity online in the near term. It says it is working with its partners to do so. All affected customers have been kept informed throughout, it says, and their plans are being accommodated.
The shift reaches the company's guidance for the year. With a portion of this year's revenue moving into the first part of next year, Nebius now expects 2026 revenue at the low end of its range.
Its Own Sites, Its Contracted Power and Its Risks
Nebius says it prefers to build its own sites, and that these are on time or ahead of schedule. It expects them to account for the majority of the capacity it brings online from 2027 onwards.
Under a heading on its owned sites, the letter says Nebius has secured all the power and components it plans to bring online in 2027. The new owned sites it expects to deploy capacity that year represent, at scale, more than 3 GW, which it expects to be delivered over the next 3 to 3.5 years.
On contracted power, the letter says Nebius now has more than 4 GW. It expects to have 5 GW by the end of 2026.
The letter calls statements about its capacity buildout plans forward-looking, and says they are not a guarantee of future performance. Among the risks it lists is bringing additional data center capacity online on a timely and cost-effective basis, including securing suitable sites and access to power. Many of these risks, the letter says, "depend on the actions of third parties and are largely outside of our control."