Energy Transfer runs natural gas pipelines, among other energy assets. Its slides for the third quarter of 2026, dated November 3, list agreements to provide natural gas, some of them for data centers.
Since the beginning of 2025, the company says, it has executed "over 9.5 million MMBtu/d" of agreements with what it calls demand pull customers, "including hyperscalers and power plants." The slides do not say how much of that is for data centers.
A table of announced projects gives several of the gas supply lines a status. Parts of the deck follow, not the whole.
Agreements for Data Centers and AI Campuses
One customer has signed multiple long-term agreements for about 900,000 MMBtu a day. The gas is for three U.S. data centers, two of them in Texas.
Other agreements support a campus under construction in Central Texas. The slides call it an AI hyperscale campus, powered by on-site natural gas generation. Initial volumes are expected to be about 150,000 MMBtu a day. A footnote says the transporter has certain rights to increase capacity "upon election."
Another agreement is with a hyperscaler. It is to support construction of facilities to provide natural gas to an AI factory campus in Abilene, Texas, at 250,000 MMBtu a day.
For a new data center site in Arkansas, the slides list a "Precedent Agreement" for firm gas transportation through the EGT pipeline.
In that table, the status of the gas supply line for the three data centers reads "TX pipes ready for service." The line for the Central Texas campus reads Q4 2026. The line for the Arkansas site reads mid-2027.
Power Plants and the Hugh Brinson Pipeline
On the power plant side, two agreements cover firm gas transportation from the MRT pipeline to two new power plants being built in Missouri. They are expected to provide a total of about 150,000 MMBtu a day. The table lists those agreements as beginning in late 2027 and mid-2028.
The Hugh Brinson pipeline has a slide of its own, whose heading names Texas markets and data center and AI growth. Its first phase is in service, with a capacity of about 1.5 Bcf a day. The second phase includes added downstream compression and is expected in service in the first quarter of 2027.
On full completion, the pipeline is expected to be able to transport over 2.3 Bcf a day from west to east. Shipper contracts, the slide says, are coming online in stages, on the dates set in each agreement.
Negotiations and the Deck's Caveats
The company says it remains "in advanced negotiations" with multiple power plants, data centers and other demand-based customers, to provide what it calls "significant volumes." It gives no number for them.
Its second slide says statements about future events are forward-looking and subject to risks and uncertainties. The same slide says references to the capacity of a pipeline "relate to maximum capacity under normal operating conditions." For pipeline transportation capacity, it adds, multiple factors "may reduce the throughput capacity from specified capacity levels."
Sources
- Energy Transfer LP. Q3 2026 Earnings (presentation). November 3, 2026 (printed on the cover). company results call